Skip to main content
Translate
Default
English
Español
Français

User Access


Information pinned ad
RLW pinned ad
Leap -  Ad - Empowering Contractors
asdf12
Tremco -  Ad - Spring Into Action With a Roof Inspection
Forum pinned ad
Translate
Default
English
Español
Français

Just wondering

« Back To Roofers Talk
Author
Posts
August 17, 2017 at 8:15 p.m.

Patty Cakes

My neighbor is having her roof done, it is an ordinary early 70's ranch attached garage, I'm guessing 20 sq. up the front down the back, no valleys, you couldn't get simplier than that. Today is day 3, equipment still there so a day 4 comes into play. Three men and a young boy... is this the norm? I know it has been 10 years since I've been involved in roofing BUT my guys would have had it done in a day, finish flashing the next and done. Any input? Or were my guys just that good?

August 17, 2017 at 8:48 p.m.

clvr83

They aren't every day roofers and have to think about every move. If they were paying my overhead, they wouldn't be making much money.

My crew of 10 guys did 40sq off and on Monday w/ 6 valleys and two chimneys. 4/12 go fast roof. 10 hours. I had an extra laborer that day, I don't normally like that many men on one roof unless it's the right roof.

Next day I had 5 guys(that's why I keep a large crew) that replaced 20sq in 10 hours, little more step flashing on this one.

August 17, 2017 at 9:56 p.m.

twill59

My partner and I plus the buggy----2 days.

August 18, 2017 at 7:20 p.m.

Patty Cakes

Update: the roof is done, equipment still there. Day 4

clvr83 you are correct....not every day roofers.

twill...no doubt


« Back To Roofers Talk
You must be logged in to reply to this topic.

Sheridan Tools - Banner Ad - May 2022
Translate
Default
English
Español
Français

User Access


RClub pinned ad
asdf12
Directory pinned ad
Forum pinned ad
Metalforming -  Ad - April 2022
Information pinned ad

Loading…
Loading the web debug toolbar…
Attempt #